Multi-Year High-Voltage Power System Planning Considering Active Power Curtailment
Zusammenfassung
Integrating active power curtailment (APC) of renewable energy sources (RES) in power system planning reduces necessary investments in the power system infrastructure. In current target grid planning methods, APC is considered by fixed curtailment factors without considering the provided flexibility to its full extent. Time-series-based planning methods allow the integration of the time dependency of RES and loads in power system planning, leading to substantial cost savings compared to the worst-case method. In this paper, we present a multi-year planning strategy for high-voltage power system planning, considering APC as an alternative investment option to conventional planning measures. A decomposed approach is chosen to consider APC and conventional measures in a long-term planning horizon of several years. The optimal investment path is obtained with the discounted cash flow method. A case study is conducted for the SimBench high-voltage urban benchmark system. Results show that the time-series-based method allows for reducing investments by up to 84% in comparison to the worst-case method. Furthermore, a sensitivity analysis shows the variation in total expenditures with changing cost assumptions.
Zitierform
In: Energies Volume 13 / Issue 18 (2020-09-19) , S. 4920 ; EISSN 1996-1073Förderhinweis
Gefördert durch den Publikationsfonds der Universität KasselZitieren
@article{doi:10.17170/kobra-202009301860,
author={Schäfer, Florian and Braun, Martin},
title={Multi-Year High-Voltage Power System Planning Considering Active Power Curtailment},
journal={Energies},
year={2020}
}
0500 Oax 0501 Text $btxt$2rdacontent 0502 Computermedien $bc$2rdacarrier 1100 2020$n2020 1500 1/eng 2050 ##0##http://hdl.handle.net/123456789/11852 3000 Schäfer, Florian 3010 Braun, Martin 4000 Multi-Year High-Voltage Power System Planning Considering Active Power Curtailment / Schäfer, Florian 4030 4060 Online-Ressource 4085 ##0##=u http://nbn-resolving.de/http://hdl.handle.net/123456789/11852=x R 4204 \$dAufsatz 4170 5550 {{Energieversorgung}} 5550 {{Planung}} 5550 {{Hochspannung}} 5550 {{Strategische Planung}} 5550 {{Zeitreihe}} 5550 {{Netzausbau}} 5550 {{Netzplanung}} 7136 ##0##http://hdl.handle.net/123456789/11852
2020-10-06T12:33:06Z 2020-10-06T12:33:06Z 2020-09-19 doi:10.17170/kobra-202009301860 http://hdl.handle.net/123456789/11852 Gefördert durch den Publikationsfonds der Universität Kassel eng Namensnennung 4.0 International http://creativecommons.org/licenses/by/4.0/ power system planning high-voltage curtailment multi-year long-term planning time series network expansion planning 600 Multi-Year High-Voltage Power System Planning Considering Active Power Curtailment Aufsatz Integrating active power curtailment (APC) of renewable energy sources (RES) in power system planning reduces necessary investments in the power system infrastructure. In current target grid planning methods, APC is considered by fixed curtailment factors without considering the provided flexibility to its full extent. Time-series-based planning methods allow the integration of the time dependency of RES and loads in power system planning, leading to substantial cost savings compared to the worst-case method. In this paper, we present a multi-year planning strategy for high-voltage power system planning, considering APC as an alternative investment option to conventional planning measures. A decomposed approach is chosen to consider APC and conventional measures in a long-term planning horizon of several years. The optimal investment path is obtained with the discounted cash flow method. A case study is conducted for the SimBench high-voltage urban benchmark system. Results show that the time-series-based method allows for reducing investments by up to 84% in comparison to the worst-case method. Furthermore, a sensitivity analysis shows the variation in total expenditures with changing cost assumptions. open access Schäfer, Florian Braun, Martin doi:10.3390/en13184920 Energieversorgung Planung Hochspannung Strategische Planung Zeitreihe Netzausbau Netzplanung publishedVersion EISSN 1996-1073 Issue 18 Energies 4920 Volume 13 false
Die folgenden Lizenzbestimmungen sind mit dieser Ressource verbunden: